Site installation begins with attending coordination meetings and working within the project schedule. Due to the sensitivity of electronic components, equipment deliveries and final install and connections cannot be done until all of the construction is completed, the point where the site is broom clean and fairly dust free, any time sooner to attempt the installation will compromise the lifespan of the equipment.

What can be done early on in the construction phases are the pulling of cable, installation of blocking (typically done by the GC), installation of projection screens, ceiling speakers (typically done by ceiling contractor), and projector and flat panel mounting brackets.